Hurst Construction LLC working under contract to the City of Oak Ridge Public Works Department is presently doing rehabilitation work on the City’s gravity wastewater collection system.  Two road closures will be necessary during the week of February 3rd to allow replacement of a total of three line sections.

On Monday, February 3rd and Tuesday, February 4th, West Arrowwood Road will be closed from 7:00 a.m. to 7:00 p.m.  Arkansas Avenue, South Alabama Road, Cedar Road and California Avenue may be used as detours.

From Tuesday, February 4th through Thursday, February 6th, East Tennessee Avenue between Turner Road and Florida Avenue will be closed from 7:00 a.m. to 7:00 p.m.  Tucker Road may be used as a detour.

Local traffic may access residences and business in the area.  This schedule is subject to change in the event of inclement weather. 

Press release information contact Roger Flynn, P.E. Public Works Engineer (865) 425-1816.

News media contact Candice Brogan at (865) 425-3546 or cbrogan@oakridgetn.gov.