The Public Works Department will begin sewer line installation on Scarboro Road beginning May 2, through June 1, 2014.  The installation will be from Bethel Valley north to the crest of Scarboro. Crews will be working on Fridays through Sundays for the next five weeks. 

The work will require sections of the road to be down to one lane traffic for those days from approximately 6:30 am and ending at approximately 8:30 pm.  Signage and flaggers will guide traffic through the affected areas.

Questions or comments can be directed to the City of Oak Ridge, Public Works Department at (865) 425-1875.

Media contact Candice Brogan at (865) 425-3546 or cbrogan@oakridgetn.gov